A review on prospective risks and mitigation for oil and gas projects: implication for Indian CGD companies

A review on prospective risks and mitigation for oil and gas projects: implication for Indian CGD companies

This research identifies the top ten risks frequently impacting the oil and gas projects, which are project cost, improper project management, change in economic parameters, currency exchange rate, government regulations and laws, contractor and subcontractors issues, lack of skilled labor, delay in approvals, health and safety issues and force majeure.

Authors

T. Joji Rao, Professor, Jindal Global Business School, O.P. Jindal Global University, Sonipat, Haryana, India.

Atul Rawat, Department of Energy Management, University of Petroleum and Energy Studies, Dehradun, Uttarakhand, India.

Sumeet Gupta, Department of Finance and Accounting, University of Petroleum and Energy Studies, Dehradun, Uttarakhand, India.

Summary

This study aims to focus on identifying the business risks that cause a delay in the oil and gas projects and suggest the way forward toward the better development of the city gas distribution (CGD) sector in India by suggesting the appropriate mitigation strategies.

Methodology

The study is a systematic review of literature on risks causing a delay in oil and gas projects. Comprehensive literature was carried out following a seven-step model to develop an exhaustive list of risk classifications and factors, risk identification methods and strategies to mitigate the risks. Weighted average ranking method is used to identify the top ten risks affecting oil and gas projects.

Findings

This research identifies the top ten risks frequently impacting the oil and gas projects, which are project cost, improper project management, change in economic parameters, currency exchange rate, government regulations and laws, contractor and subcontractors issues, lack of skilled labor, delay in approvals, health and safety issues and force majeure. These risks are primarily responsible for cost overrun and project delay. Additionally, this study recommends the implementation of joint risk management to avoid CGD project delay.

Originality

The CGD industry is in the growing stage with many projects under construction. However, there is a lack of research to manage risks in the CGD project. This study contributes to the limited literature available on risk management in oil and gas projects. Additionally, it highlights the need for further research to explore the different risks factors affecting the CGD business and its operations and subsequently develop appropriate mitigation strategies.